1.            Enhancement of Irrigation Throgh Surface Water Augmentation in Greater Dinajpur & Joypurhat District.; (October-2020- December'2025). Estimated cost: Org: Tk. 25114.79 lakh; Rev. Tk. 28867.79 Lakh.

 

Objective of the project :

1) Bringing non-irrigated land of the project area under irrigation.

2) Expansion of irrigation and removal of water logging by creating water reservoir & conserving rain water. For this-

a) Re-excavation of 200 km Khals & 100 nos. water body and construction of 37 nos. submersedweir

b) Installation of 155 nos. solar/electric LLPs and other facilities in the project area.

c) To produce 2.32 lakh MT crop every year by irrigating 26506 hectares of land using 155 nos. of solar/electric LLP.

d) Bringing 306 hectares submersed land under agricultural production by removing water logging.

e) Ensuring low water consuming crop /vegetable production by excavating 60 nos. of Dugwells.

f) Reduce the use of electricity for irrigation through the use of renewable solar energy.

g) To create additional forest resources, meet nutritional needs and help in environmental development by planting 2 lakh trees.

h) To create opportunities for farmer training and self-employment in the project area.

(Lakh Taka)

Components

DPP

Target

Achievement

up to

September, 2025

For the year 2025-26

Cumulative

Expenditure (%) Physical %

ADP Allocation

Fund

released

Expenditure (%) physical%

Plantation (Fruit, Forest & Medicinal) (Nos.)

200000

200000

655.00

327.50

301.77 (46.07%)

64.63%

28150.14

(97.51%)

99.98%

Farmer Training (Person)

1500

1500

Construction of Zonal office (Nos.)

4

4

Construction of Store Cum Zonal office (Nos.)

6

6

Construction/repair of office boundary (Nos.)

5

4

Digging of DugWell (Solar and pipeline) (Nos.)

60

60

Re-excavation of khal/khari (km.)

200

200

Re-excavation of Water Body (Nos.)

100

100

Construction of Sub-merged weir (Nos.)

37

37

Construction of uPVC Pipeline (250 mm dia) (Nos./km.)

155/232.50

155/232.50

Extension of uPVC pipeline Each-590m (Nos./km.)

1500/885

1460/861.40

Installation of Solar LLP (Nos.)

125

125

Installation of Electric LLP (Nos.)

30

30

Water drainage Pipe Line (625mm dia) (Nos.)

2.50

2.50

 

 

 

 

2.            Rehabilitation of Irrigation Infrastructure Project; (January' 2022 - December' 2026).

Estimated cost: Tk. 32298.71 lakh.

 

Objective of the project :

a) To maintain irrigation facilities by rehabilitating old 6654 nos. Deep tubewells;

b) To produce 3.26 lakh M: tonnes of crops annually by ensuring irrigation of 40740 hectares of land;

c) To prevent of wastage of irrigation water through repair/renovation of irrigation canals;

d) Increasing the efficiency of irrigation equipment;

e) To improve the quality of life of about 54 thousand people in the project area through agricultural work.

(Lakh Taka)

Components

DPP

Target

Achievement

up to

September, 2025

For the year 2025-26

Cumulative

Expenditure

(%)

Physical %

ADP Allocation

Fund

released

Expenditure (%) physical%

Rehabilitation of old deep wells (Nos.)

1358

1200

6500.00

1455.00

1285.00 (19.77%)

47.48%

26960.62 (83.47%)

93.62%

Reconstruction of old unusable pump house (Nos.)

2309

2180

Repair of old pump house (Nos.)

2987

2918

Reconnect the Electric line (Nos.)

1358

1200

Installation of riser valves and repair of outlets (Nos.)

36789

32260

Electrical line repair (Nos.)

300

283

 

 

 

 

 

 

3.            Extension of Irrigation in Barind Area Through Conservation of Water in Canal-2nd Phase; (October,2022-June'2027). Estimated cost: Tk. 24940.00 lakh.

 

Objective of the project :

a) To increase the use of surface water from 10% to 12% in the project area for irrigation.

B) To increase the irrigation facilities by using surface water in 3490ha (approx) land.

c) Environmental improvement through plantation besides canals and ponds.

(Lakh Taka)

Components

DPP

Target

Achievement

up to

September, 2025

For the year 2025-26

Cumulative

Expenditure

(%)

Physical %

ADP Allocation

Fund

released

Expenditure (%) physical%

Purchase of pontoons and accessories

4

4

6607.00

1651.75

1324.49

(20.05%)

25.14%

17850.015

(71.57%)

74.65%

Pontoon repairs and ancillary works

2

2

Re-excavation of Khas khal/khari (km.)

38.25

29

Re-excavation of the pond (No.)

1

1

Re-excavation of the beel (Nos.)

2

 

Construction of sub-merged wire. (Nos.)

7

4

Construction of sub-mergedwire with footover bridge (Nos.)

6

4

Construction of pipe holding structures (No.)

1

1

Construction of box culverts across highways (No.)

1

 

Dismantling 250mm. Dia pipe line (km.)

42.00

42.00

Dismantling 350mm. Dia pipe line (km.)

11.10

11.10

Road demolition and reconstruction, bitumen carpeting (km.)

2.30

2.30

Construction of 250mm. Dia uPVC pipe line (km.)

132

71

Construction of 250mm. dia underground MS pipe lines (km.)

16

8

Construction of 450/500 mm. dia HDPE pipe line (km.)

38.70

25.50

Construction of 450/500mm. dia underground MS pipe lines (km.)

34

13.60

Construction of river banks, pump landing station, pump house etc (Nos.)

8

6

Construction of RCC structure at water fall site (Nos.)

7

5

Construction of electric lines (km.)

13

9

Installation and commissioning of transformers (Set.)

16

12

Installation and commissioning of pumps (Set)

26

20

 

 

4.            Program on Agricultural and Rural Transformation for Nutrition, Entrepreneurship and Resilience (PARTNER) (July' 2023 - June' 2028). Estimated cost: Tk. 11092.00 Lakh (GOB: Tk.709.00 Lakh; DPA: Tk. 10383.00 Lakh);

 

Objective of the project :

1. Fruits and Vegetables with GAP certification - Increase area under cultivation.

2. Expansion of new areas under high yielding rice varieties.

3. Increasing the area under cultivation of non-rice grains, pulses, oilseeds and horticulture crops.

4. Bringing new land under cultivation under improved and efficient irrigation technology.

5. Ensuring proper administration and availability of agricultural services (such as extension assistance, fertilizer seed and other input assistance and agricultural credit assistance) through "Farmer Smart Card" system.

6. Accreditation and promotion of seed certification and food safety testing

7. Providing training to youth and women entrepreneurs in commercial agriculture, agribusiness, agricultural innovation and agricultural services

8. Development of an operational evaluation system for NARS institutes and extension systems along with enhancement of research activities for new technologies and innovations to enhance the capacity of institutions

9. Establishment and operationalization of promotional organizations in at least five value chains for selected agricultural products.

10. Quality development of integrated digital agricultural information services including agricultural statistics and international markets.

(Lakh Taka)

Components

DPP

Target

Achievement

up to

September, 2025

For the year 2025-26

Cumulative

Expenditure

(%)

Physical %

ADP Allocation

Fund

released

Expenditure (%) physical%

Installation of Solar system for existing DTW.

80

72

1020.00

255.00

32.84

(3.22%)

3.70%

8922.75

(80.44%)

80.54%

Installation of Solar LLP

50

48

Installation of New Solar DTW in Char land

50

40

Construction of buried pipe line for LLP (each 610 m) with supply of 250 mm dia uPVC pipes, fittings and riser valves etc. (package)

50

48

Construction of buried pipe line for DTW in Char land ( each 610 m) with supply of 250 mm dia uPVC pipes, fittings and riser valves etc. (package)

50

42

Installation of Drip Irrigation System

10

 

Installation of Sprinkler Irrigation System

10

 

Installation of Sensor based irrigation System

1

 

 

 

5.            Water supply from Padma river and extension of irrigation in Barind area by double lifting system. (September' 2023 - June' 2027). Estimated cost: Originaj: Tk. 54805.68 Lakh (GOB); Rev.: Tk. 54803.28 Lakh (GOB)

 

Objective of the project :

To produce additional crops by expanding irrigation in the Barendra area, including optimal use of groundwater in the project area, prevention of irrigation water wastage, and increasing groundwater recharge through the development of modern and sustainable irrigation systems.

• Increase groundwater recharge and control groundwater table depletion through the use of surface water in the project area.

• To increase the water holding capacity of the canals by re-excavating 120 km of Maja Canal in the project area and to provide year-round irrigation to the command areas on both banks of the canal by diverting the water of the Padma River into the said canals.

• To increase the current irrigated area through groundwater in the project area from 2012 ha or 2.56% to 12262 ha or 15.60% and reduce pressure on groundwater. sides of the canal by channeling the water of the Padma River into the said canals

• By supplying water from the Padma River for irrigation purposes in the Barendra region, 18 km away from the Padma River and 35 meters (115 feet) above sea level, the project area has been upgraded from 10,250 hectares of single-crop land to three-crop land, bringing it under irrigation and producing an additional 1.40 lakh metric tons of crops per year, while maintaining the sustainable environment of the project area.

• Environmental development to combat climate change by planting fruit and medicinal tree seedlings on both sides of the re-excavated canal in the project area.

(Lakh Taka)

Components

DPP

Target

Achievement

up to

September, 2025

For the year 2025-26

Cumulative

Expenditure

(%)

Physical %

ADP Allocation

Fund

released

Expenditure (%) physical%

Construction of Box Culvert (for Road crossing) (Nos.)

3

 

22185.00

5546.25

4480.55

(20.20%)

20.52%

12824.29

(23.40%)

26.93%

Construction of Sub merged wire (Nos.)

32

3

Supply, Installation and Commissioning Centrifugal pump, prime mover and hose pipe for intake pump station (nos.)

7

 

Construction of floating barge/pontoon  (Intake station and delivery point) (Nos.)

1

 

Supply, Installation and Commissioning of Centrifugal Pump, Prime Mover and related equipments for Booster Pump Station. (Nos.)

12

 

Construction of 120  Cusec discharge Booster Pump station with pump base (Nos.)

2

 

Procurement of 250 mm dia uPVC Pipe (for LLP) (M.)

160000

 

Procurement of Solar cum Electrified LLP & Net Metering with other Irrigation equipment (Nos.)

160

 

construction of LLP & Net Metering with other Irrigation structure  (Nos.)

160

 

Procurement of Drip Irrigation equipment (Nos.)

10

 

Installation of Drip irrigation system with associated equipment (Nos.)

10

 

Procurement of 1000 mm dia HDPE pipe with fittings (m.)

37000

22094

Installation of 1000 mm dia HDPE pipe with fittings (m.)

18500

7700

Re Excavation of khal (km.)

120

30

Procuring of Electrification materials for construction of electric line (11 KVA) (Km.)

118

5

Procuring of Electrification materials for construction of electric line (11 KVA) (Km.)

25

 

Procurement of Tele pre paid meter for LLP (Nos.)

320

 

Installation of Tele pre paid meter for LLP (Nos.)

160

 

Setting up of 20 MVA sub-station ( Intake pump=10 MVA, Booster pump 5+5=10 MVA)  (No.)

1

 

Plantation (Fruit & Medicinal) (Lakh)

1.99

0.85

 

 

 

 

 

6.            Project for Capacity Building Acceleration Including Infrastructure Development of Barind Multipurpose Development Authority. (October,2023- June,2026). Estimated cost: Tk. 4055.00 Lakh (GOB);

 

Objective of the project :

1. Construction of modern office buildings for development of agricultural work, monitoring, increasing mobility and proper management of proper supervision.

2.To create a better working environment for performing fair work by avoiding obsolete, unsanitary, hazardous.

3. To provide modern and advanced training on agriculture/irrigation including office management, procurement policy, modern irrigation management, SDG, APA, Delta Plan etc. for capacity building of authority officers/parties.

(Lakh Taka)

Components

DPP

Target

Achievement

up to

September, 2025

For the year 2025-26

Cumulative

Expenditure

(%)

Physical %

ADP Allocation

Fund

released

Expenditure (%) physical%

Construction of Head Quarter office building (Sqm.)

7680

1736

2479.00

619.75

13.373

(0.54%)

0.54%

1287.57

(31.75%)

41.06%

Construction of Zone office Building (1 no.) (Sqm.)

335

335

 

 

 

7.            Popularize of High Value Unconventional Fruit & Medicinal Crop in Barind Area Project;

(July-2020- June'2026). Estimated cost: Org.: Tk. 1733.82 lakh; Rev.: Tk. 2906.63 lakh.

 

Objective of the project :

a) For the shake establishing  high value non-conventional fruits and medicinal crops garden in farmers' own land or homestead area dispute saplings free of cost.

b) Establishment of demonstration farms of high value non-conventional fruits and medicinal crops in the Barind area..

c) Provide training to farmers / officers-staffs on production of high value fruit and medicinal saplings, planting etc.

(Lakh Taka)

Components

DPP

Target

Achievement

up to

September, 2025

For the year 2025-26

Cumulative

Expenditure

(%)

Physical %

ADP Allocation

Fund

released

Expenditure (%) physical%

Farmer's Training (Person)

1500

1380

410.00

102.50

82.349 (20.09%)

24.18%

2431.816 (83.66%)

85.63%

Officer/Employee Training (Person)

270

270

Demonstration farming (Nos.)

100

92

Purchase of sapling (Nos.)

416800

383800

Purchase of seeds (Nos.)

5050

5050

 

 

 